Setting Out: Work from the Datum and the Grid Lines
Updated: Nov 2
In my view, one sign of a good bricklaying contractor is that they can set out their own work from the grid lines, without help from the site manager or the carpenter. That takes some basic carpentry skills, and I think they are worth learning. A good set-out comes down to two things, and the drawings decide both. When the site needs something different, there is a third step.
The issue
Sometimes a site manager is too busy and says something like "just go 3.5 m up from the slab", and walks off. It sounds simple. But slabs are rarely perfectly level. If every height is measured up from the slab, any error in the slab carries straight into the wall, and the top of the wall follows the slab instead of the drawings.
The problem shows up later, when the windows, the steel or the next floor do not line up. Then the question is whose work is out, and that is checked against the drawings, not against what was said on site. In my view, there is a good chance the responsibility comes back to the bricklayer.
A harder case is when the site manager's instruction is not based on the RL or the grid lines, because access is limited or for some other reason. Following site instructions matters too, and there is often a good reason behind them. But if the instruction is only spoken, nothing shows later why the wall does not match the drawings. The subcontractor only followed the instruction on site, yet can end up carrying the whole responsibility.

Height from the datum, position from the grid lines.
The solution
Height from the datum. Find the datum from the RL on the drawings and the one site management has set, using a dumpy level or a good laser level. Take every height from that datum, not from the slab.
Position from the grid lines. Use the grid lines to work out the exact length and measurements of every wall you will build, before the first course. Know exactly what you are building and where it sits.
When the site instruction is different, get it in writing. If access is limited, or there is another reason to work from a different reference, follow the instruction, but get it in writing before you build: what reference to use, how it differs from the drawings, why, who gave it, and the date. An email or a signed note is enough, ideally from the person your contract allows to give directions.
In my view, if you set out from the datum and the grid lines and comply with them, you have the strongest defence you can have. If something is found to be out later, you can show that your work matches the drawings, or, where it does not, the written instruction that explains why.
Setting out takes time at the start of a job, but it decides whose problem a mistake becomes later.
Every contract is different. These are, of course, only my own views. If you see things differently, I would like to hear from you.