Understanding the CA's and PM's Perspective
Updated: Nov 2
From the point of view of a contract administrator (CA) or project manager (PM), the bricklaying package is often not a welcome one. Part of the reason is the nature of our businesses. Most bricklaying companies stay small, and they cannot grow to the size of other trades or suppliers. There are exceptions, but in my experience the number of bricklaying contractors who properly understand contract terms and clauses is very small.
The biggest conflict is a difference in viewpoint. Many of us work as a form of labour supply. We believe that if the work is good and finished on time, our job is done. The CA, however, looks at the job from a project management point of view, and asks whether the work can be carried out in line with every clause and condition of the contract. On that question, bricklaying contractors often cannot give a guarantee, or enough confidence.
As a result, bricklayers are often put on the "watch out" list. Once a job runs that way, the more work we do, the less we are treated as a partner in the project and the more we are treated as a labour supplier who is simply paid for the work. That leads to situations nobody enjoys. In this post I look at what CAs and PMs actually want.
Who they answer to
It helps to start with their position, at least as I have seen it. In many cases a CA or PM does not decide alone. A subcontract they recommend often has to be approved by someone above them, such as a commercial manager or a director, and sometimes by the client as well. A variation they accept may need to be explained, and a delay accounted for in the program. That said, it is not always the same. Some CAs and PMs are given a good deal of authority and act on their own judgement, and the way they work can differ from one company, and one project, to the next. Either way, when a subcontractor creates a problem, it is usually the CA or PM who has to deal with it first.
What the CA wants
I cannot speak for every CA, and each one works in their own way. In my view, though, a CA is likely to welcome a quote that is clear and complete. A gap found after the contract is signed can turn into a variation, and an unexpected variation is often something the CA then has to explain.
After award, I think a similar way of thinking carries into the contract itself. I believe most CAs would appreciate a subcontractor who has read the contract, including the special conditions, and who raises questions before signing rather than after. It probably also helps when insurances, safety documents and licences are current and provided at the start without reminders, and when payment claims arrive on the date and in the format the contract sets out, with the supporting records attached.
What the PM wants
The PM looks at the same job through the program. Brickwork and blockwork often sit on or near the critical path: windows, roofing, services and finishes follow us. What the PM wants, therefore, is mostly certainty.
A program they can rely on, with crew numbers that match it.
Early warning. If a delivery is late, a drawing does not work on site, or a hold point is coming up, they want to hear it early and in writing, not at the end of the week.
Notices on time. Most subcontracts set time limits for notices of variations and delays. A late notice is a problem for both sides, and it can mean a valid claim is lost.
Records. Daily reports, photos and inspection records that show what was done, and when.
One point of contact who answers the phone and can make a decision.
From labour supply to partner
None of this needs a large company. It needs a different habit: reading the contract as carefully as the drawings, putting things in writing, and treating the paperwork as part of the job rather than something in its way. When a bricklaying contractor works like that, the CA has less to worry about and the PM has fewer surprises. That is when we stop being a trade to watch and start being treated as a partner in the project.
Still learning
I have signed a good number of contracts myself, and I still make mistakes. I am still learning.
To me, a good bricklaying contractor is one who goes through the job documents thoroughly and can see ahead: where variations are likely to come up, and how they will be agreed. Then, when they do come up on site, they are settled the way both sides expected instead of turning into conflict, and the contractor can act as a mediator rather than one side of an argument.
One of the things CAs and PMs dislike most is a variation the contract did not anticipate. How it is handled will depend on where it came from, of course. But going through these points together before work starts is the best way to build trust on both sides.
Once work starts, we will meet many problems nobody saw coming. Foresight, so that both sides are prepared for them as far as possible, is the key.
This is how I see it from the subcontractor's side. These are, of course, only my own views. If you see things differently, I would like to hear from you.