What a Variation Is, and Why It Belongs in Writing

Writer: Yohan Park
Yohan Park
Nov 1
2 min read

Updated: Nov 2

Most of us have been asked on site to do something extra while we are there: an extra pier, a wall moved a little, a different brick on one elevation. Often it is small. But under a subcontract, a change to the agreed work is usually a variation, and how it is handled can decide whether it is paid.

What a variation is

A variation is a change to the scope of work in the contract: an addition, an omission, or a change to how, where or when the work is done. Most subcontracts have a clause that says who can direct one, how, and how it is valued. It is worth finding that clause before the job starts.

Why it belongs in writing

  • Who can direct it. Many subcontracts only count a written direction from a named person, often the CA or PM. A verbal request from someone else may not be enough.

  • Time limits. Many contracts set a time limit for notice. A late notice can weaken or lose a claim, even for work that was clearly extra.

  • Memories fade. Months later, at the final account, nobody may remember exactly what was said on a Tuesday morning.

A simple habit

  1. Ask who is directing the change, and whether a written direction will follow.

  2. If work has to continue, confirm it in writing the same day: what was asked, by whom, and when.

  3. Record the work as it is done: photos, quantities, labour and materials.

  4. Give notice within the contract's time limit, then submit the price with the records attached.

A simple habit for variations: ask who is directing it, confirm in writing the same day, record the work, then notice and price

Not every change is a variation. Some things that feel extra are already in the scope, or are the subcontractor's own responsibility, which is another reason to read the scope and exclusions before signing. As I wrote in Understanding the CA's and PM's Perspective, going through these points together early is one of the best ways to build trust.

This is general information from a bricklaying contractor's point of view, not legal advice. Every contract is different. These are, of course, only my own views. If you see things differently, I would like to hear from you.

artvisionbrickwork@gmail.com · Artvision Brickwork

Recent Posts

See All
Bricklayer and contractor

The usual way into the trade in Victoria is the Certificate III in Bricklaying and Blocklaying (CPC33020), normally a three-year apprenticeship: paid work on site, with blocks of study at TAFE. (1) On

 
 
 

Comments


bottom of page