At the base of a brick veneer wall on a slab, two requirements can pull against each other: where the damp-proof course (DPC) and weep holes have to go, and how high they have to sit above the paving outside. Here is the problem, and the way it is usually solved.

The issue

Weep holes go in the course immediately above the DPC, so the cavity can drain. The DPC itself generally needs to sit low, at the slab edge below the internal floor level, so that water from outside cannot find its way towards the house.

But the NCC Housing Provisions also set a minimum height for the DPC above the surface outside: for example, 75 mm above paved or concreted areas that slope away from the wall. When a concrete path is poured high, the weep holes on that side can end up only about 20 mm above it.

Section through the base of a brick veneer wall on a slab: the DPC turned up behind the sarking, a weep hole in the course above it, and a concrete path poured only about 20 mm below the DPC instead of the 75 mm minimum.

The conflict at the base of the wall. Illustrative detail, not to scale.

The solution

In my experience, keeping the DPC low at the slab edge generally comes first, because that is what keeps water out of the house. Where the external weep holes end up only around 20 mm above the path, talk to the engineer, agree an alternative (performance) solution and have it approved, and prepare it for the building surveyor. It is usually easier to raise this early, when the levels are first checked, than after the path is poured.

Installing the DPC

  • Slip the DPC in behind the sarking, so water running down the sarking lands on the DPC and not behind it.

  • Lap it by 150 mm and turn it up at the back of the cavity.

  • Seal any cuts with a tape certified as waterproof.

  • Keep it continuous through the wall and visible at the face, and keep the cavity and weep holes clear of mortar.

This is general information, and every site is different. Check the drawings, the NCC edition that applies, and the building surveyor. These are, of course, only my own views. If you see things differently, I would like to hear from you.